Defense Contracts: Better Monitoring Could Improve DOD's Management of Award Lead Times

GAO-24-106528 Published: Mar 14, 2024. Publicly Released: Mar 14, 2024.
Jump To:

Fast Facts

Before awarding contracts, the government needs time for tasks like evaluating proposals and negotiating to ensure taxpayer funds are spent wisely. That priority is balanced with the need to deliver goods and services quickly. The Department of Defense is working to reduce the time needed for awarding contracts. Award lead times can be a good indicator of contract timeliness.

Over the last 4 years, DOD award lead times decreased overall. But lead times grew for contracts valued over $50 million. Also, DOD doesn't track department-wide trends, and there are gaps in award lead time data it has collected.

Our recommendations address this.

A contract with a pen and magnifying glass resting on top it and an hour glass next to it.

Skip to Highlights

Highlights

What GAO Found

The length of time between when an agency solicits offers from potential contractors and the date it awards a contract is known as the procurement administrative lead time (PALT). GAO found that median award lead times, or PALT, generally decreased from fiscal year 2019 through fiscal year 2022 for Department of Defense (DOD) contracts and orders valued above $250,000. This suggests that DOD has realized some contracting efficiencies since 2018 when it began collecting data to measure PALT. However, PALT varied by characteristics such as total contract value, contracting approach, contract type, extent of competition, and the type of product or service procured. For example, median PALT values increased by 70 days over the four-year period GAO reviewed for DOD contracts and orders valued over $50 million.

Change in DOD-wide Median Procurement Administrative Lead Time for All DOD Contracts and Orders Above and Below $50 Million in Value, Fiscal Years 2019–2022

Change in DOD-wide Median Procurement Administrative Lead Time for All DOD Contracts and Orders Above and Below  Million in Value, Fiscal Years 2019–2022

After its adoption of the current PALT definition, DOD updated guidance to encourage the use of practices intended to reduce award lead times. For example, DOD reissued its Source Selection Procedures memorandum in August 2022, adding streamlining techniques for procurement officials to consider. These techniques generally reflect practices to reduce PALT that were suggested in a January 2021 Office of Management and Budget memorandum.

While updating guidance is a positive step, DOD does not have insight into PALT at the department-wide level, in part for the following reasons:

  • DOD officials do not regularly monitor PALT on a department-wide basis, such as by reviewing PALT data maintained by the defense components or discussing PALT changes with the components.
  • A DOD tool, the PALT Tracker, implemented in February 2019 for the detailed tracking of PALT for procurements over $250 million in value, has data gaps, which limits its usefulness as a monitoring tool. Components reported that it is burdensome and duplicative of other systems they use.

DOD would benefit from engaging with the components to determine how existing procurement data can be leveraged to enhance DOD's visibility into PALT changes and whether the PALT Tracker is still needed. If the PALT Tracker remains necessary to supplement existing procurement data, then improvements are needed to ensure its data are complete.

Why GAO Did This Study

DOD uses contracts to procure goods and services ranging from cutting-edge military aircraft to common office supplies. DOD leadership and contractors have expressed concern about the length of time it takes to award contracts, which includes PALT. DOD began collecting data to measure PALT in June 2018 for contracts and orders valued above $250,000.

A committee report included a provision for GAO to review DOD's efforts to address PALT. This report assesses changes in PALT over a four-year period and the extent of efforts—both DOD-wide and by selected DOD components—to manage and monitor the length of time it takes to award contracts.

GAO selected the four DOD components (Army, Navy, Air Force and Defense Logistics Agency) with the most contracting activity from fiscal years 2019 through 2022 and analyzed data on PALT. GAO also reviewed relevant DOD guidance and memorandums, and interviewed officials at DOD and the selected components.

Recommendations

GAO is making 3 recommendations. These include that DOD assess how existing procurement data can be leveraged to monitor PALT across the department, determine if the PALT Tracker is necessary to supplement existing procurement data, and make improvements to its PALT Tracker if it continues to be used to track PALT for procurements over $250 million in value. DOD agreed with the recommendations.

Recommendations for Executive Action

Agency Affected Recommendation Status
Department of Defense The Secretary of Defense should ensure that the Principal Director of Defense Pricing and Contracting, in coordination with key DOD components, assess how existing procurement data can be leveraged to regularly monitor PALT across DOD to identify issues that may require action through policy or guidance, or management attention at the component level. (Recommendation 1)
Open – Partially Addressed
The Principal Director of Defense Pricing and Contracting met with the major components' Senior Procurement Executives in May 2024 and agreed upon a correction action plan that includes the measures and report formats to use to monitor PALT quarterly. In order to fully implement this recommendation, DOD needs to provide documentation from these reviews, which DOD stated that it expects to do before the end of the calendar year.
Department of Defense The Secretary of Defense should ensure that the Principal Director of Defense Pricing and Contracting, in coordination with key DOD components, determine if the PALT Tracker is necessary to supplement existing procurement data to regularly monitor high-dollar-value acquisitions. (Recommendation 2)
Open – Partially Addressed
In May 2024 agreement was reached between the Principal Director of Defense Pricing and Contracting and major components' Senior Procurement Executives (SPEs) on a corrective action plan to regularly monitor high-dollar value acquisitions using existing procurement data available from the components, and retire the PALT Tracker tool. DOD reported that it is currently taking steps to fully implement this recommendation by updating the Defense Federal Acquisition Regulation Supplement (DFARS) to remove the reference to using the PALT Tracking Tool.
Department of Defense Should the Principal Director of Defense Pricing and Contracting determine that the PALT Tracker is necessary to supplement existing procurement data, then the Secretary of Defense should take steps to improve the completeness of PALT Tracker data, such as ensuring components adopt the application programming interface to enable automatic data transfer. (Recommendation 3)
Open – Partially Addressed
In May 2024, agreement was reached on a correction action plan between the Principal Director of Defense Pricing and Contracting and major component Senior Procurement Executives to regularly monitor high-dollar value acquisitions using existing procurement data available from the components, and retire the PALT Tracker tool. DOD reported that it is taking steps to update the Defense Federal Acquisition Regulation Supplement (DFARS) to remove the reference to utilize the PALT Tracking Tool, which would obviate the need for any efforts to improve the completeness of the PALT Tracker data.

Full Report

GAO Contacts

Mona Sehgal
Director
Contracting and National Security Acquisitions

Media Inquiries

Sarah Kaczmarek
Managing Director
Office of Public Affairs

Public Inquiries

Topics

Bid solicitationsContract awardContracting officersDefense contractsFederal acquisition regulationsFederal procurementIndefinite delivery contractsMilitary forcesSource selectionGovernment procurement